PROJECT MANAGEMENT: Aramark Facilities Planning & Project Management for the Archdiocese of New York (Yonkers) Contracted Amount: $38,487.03
ARCHITECT AND ENGINEER: PC Studio Architect, PLLC (Brewster) Contracted Amount: $114,900
1) ABESTOS ABATEMENT:
(a) Abatement Company Contracted: NSC Environmental Services Inc. (Mt. Vernon) Contracted Amount: $76,625.00 Proposed Start Date: March 25 Time Line: 1 month
(b) Monitoring Company Contracted: Adelaide Environmental Health Associates, Inc. (Brewster) Contracted Amount: $23,756.00 Dates: as above
2) INTERIOR DEMOLITION AND RENOVATION: Contractor: W. B. Classical Builders LLC (Stormville) Contracted Amount: $1,162,000 Proposed Start Date: upon completion of abatement Time Line: 9 months